Sea freight from China to South Africa: planning around a 22 to 30 day lane

By Yueyang International Logistics · 7 min read

Most enquiries for cargo going to South Africa arrive as a rate request. The number that decides whether the shipment works is usually the arrival window, because a sailing on this lane is long enough that stock cover decides the outcome more often than the freight rate does.

Our published range for this lane is 22 to 30 days by sea and 12 to 18 days by air. Eight days of spread inside one published service is ordinary. Two containers booked in the same week can land a week apart, and neither booking went wrong. A reorder point built on the fast end of that range will leave you out of stock at some stage this year.

What the 22 to 30 day range covers

Door to door means the clock runs from collection at your supplier, through export clearance at the Chinese port, the ocean leg, import clearance, payment of duties and taxes, and the inland delivery. Port to port stops at the quay, and every step after that becomes yours to arrange and pay for.

Three things sit outside any transit figure. Production and packing happen before the container is collected. A container that misses a vessel waits for the next one. And the gap between a vessel berthing and a delivery slot at your warehouse depends on how busy the terminal is that week.

Ask which clock a quote uses before you set it beside another one. A port-to-port figure and a door-to-door figure can carry the same number of days and still describe different journeys, and the door-to-door one is what you plan stock against.

The gap between sea and air on this lane

The two published ranges do not overlap. Air freight lands in 12 to 18 days and sea freight takes 22 to 30. Compare the fast end of one against the fast end of the other and the gap is about ten days; compare the slow ends and it is twelve. Either way the decision is worth around a week and a half of stock cover.

Pricing that gap is arithmetic anyone can do with their own numbers. Take the gross margin the shipment earns between the day the air cargo would arrive and the day the sea cargo would arrive, then hold it against what air costs above sea for the same cartons. If the margin is larger than the difference, part of the order should fly. If it is smaller, the cargo can wait and the sea booking is the cheaper choice for the business.

The answer changes with the goods. Air freight is charged on the greater of actual weight and volumetric weight, so a light bulky carton is priced on the space it takes up. Textiles and flat-pack goods pay for air on volume, while hardware in the same carton size pays on kilos. Air only repays itself on cargo that holds a high value per kilogram, and bulky low-value goods rarely get there.

Splitting the order is often the answer. Fly the lines that are selling now and send the replenishment by sea. What matters is how much stock would otherwise be missing from the shelf, and a small part of a large order can matter more than all of a small one.

Where LCL stops being the cheaper option

LCL shares a container with other cargo, and you pay for the space you occupy, charged per cubic metre or per tonne, whichever figure is larger. There is a minimum charge, so a very small shipment pays a floor that is out of proportion to its size.

Our rule of thumb for the destinations we serve is that shipments below roughly 13 cubic metres are usually cheaper to send LCL, and shipments above roughly 20 cubic metres are usually cheaper as a full container. Between those figures the answer depends on the details, which is why both options should be quoted on the same brief.

Usable space in a container is smaller than its nominal size, because cartons and pallets leave gaps that nothing fills. As a working guide, a 20ft holds about 28 cubic metres, a 40ft about 58, and a 40ft high cube about 68.

Cargo density moves the line downwards. Steel fittings, tiles and machinery reach a container's weight limit long before they fill its space, and LCL charges by weight as well as by volume, so heavy cargo justifies a full container sooner than light cargo does.

On this lane there is a second reason to look hard at the crossover. LCL adds a consolidation at origin and a deconsolidation at destination, more handling than a sealed container, and a departure that waits until the box is full enough to sail. Those extra days sit on top of an ocean leg that already runs 22 to 30 days, and they are the part of an LCL booking that buyers forget to allow for.

What a door-to-door DDP price to South Africa has to list

DDP means Delivered Duty Paid. The forwarder stays responsible for the cargo until it reaches your address, which includes clearing import customs and paying the duties and taxes owed in South Africa.

A DDP quote should name pickup at the supplier, export clearance at the Chinese port, the ocean freight, import clearance, duties and taxes, and delivery to your address. If a quote uses the term and then leaves duty out, ask which of the two it is excluding.

Some charges sit outside almost every quote, because they are billed in the destination country by companies the forwarder did not hire. These are worth knowing by name:

  • Terminal handling and port security charges
  • Customs examination or inspection fees
  • Storage or demurrage once the free days run out
  • Delivery outside the carrier's standard area, or to a residential address
  • Waiting time when the receiving site cannot take the vehicle
  • Unloading when the truck arrives without equipment

None of these is unreasonable on its own. The problem is when you first hear about them, which is after the cargo has arrived and there is no time left to compare alternatives.

On our DDP service they sit inside one price, and where a charge falls outside the scope we name it before booking. Ask any forwarder for the exclusions one by one, and ask how long the quoted rate holds, because a rate with no expiry date cannot be planned against.

What adds days to the sailing

A sailing that runs past 30 days has usually lost the time to one of a short list of causes:

  • Congestion at the load port or the arrival port, which delays loading and discharge
  • Blank sailings, where a carrier cancels a departure and your container is rolled to the next vessel
  • A customs examination, which holds the container while it is inspected
  • Documents that disagree with each other, such as a weight that does not match the packing list
  • Peak season, when terminals are busiest and vessels wait for a berth
  • A routing through a transshipment port, which adds a second loading and discharge cycle

The transshipment point deserves a question on a lane this long, because it is where a week can disappear while your paperwork is in order.

Two periods change the picture on every China lane. Before Chinese New Year, factories push out a month of orders in a few weeks and the ports fill up. In the autumn, carriers move seasonal stock for Western retailers and space tightens again. If the cargo has to arrive before a fixed date, book earlier than feels necessary.

Checks before you book

A quote request that produces a usable answer contains the cargo description, the carton count, the dimensions as packed, the gross weight, the supplier address in China and the delivery address. Add anything unusual: batteries, liquids, powders, magnets, branded goods, wooden packaging. Those details decide which vessels can carry the cargo and which documents travel with it.

When the order comes from several suppliers, consolidation at origin is what keeps one shipment on one schedule. Our warehouse in Yiwu receives cargo from multiple suppliers, inspects it, applies labels, repacks cartons where they can be made smaller, and releases a single consolidated shipment. Inspection at that stage catches a carton count that does not match the packing list, or a weight that disagrees with the documents, while both are still cheap to fix. Consolidating also means one set of export documents instead of one per supplier.

Ask for the container number and the bill of lading number when the cargo leaves, not when you start to worry. With those two references you can follow the vessel, and you can tell whether a delay is at sea, at the terminal or in clearance.

If the goods carry a value worth protecting, arrange cargo insurance when you book. Our cover is arranged at that point, on the declared value, so protection starts before the cargo moves.

Yueyang International Logistics has moved cargo out of China since 2010, from our office in Yiwu, by sea, air and rail. If you are planning a shipment to South Africa, send the cargo details, both addresses and your required delivery date to [email protected] or call +86 152 6732 4109. We quote within 24 hours and we tell you which part of the journey each charge belongs to.

About the author

Editorial team at Zhejiang Yueyang International Freight Forwarding Co., Ltd. — an international freight forwarder headquartered in Yiwu, Zhejiang, China, providing sea, air and rail freight plus DDP door-to-door shipping since 2010.